Highlands Sewer Relief Project Updates

Project Update - Construction Begins (posted November 24, 2021)

Post

In early December, crews and heavy equipment will start sewer construction activities on Channing Drive, continuing to Melrose Drive, Claussen Way, and Larry Drive (see map). On-street parking may be restricted in work zones (signs will be posted before work begins). Residents in the active work area can still get to their homes and driveways, but detours for through-traffic may be necessary.

Construction will proceed in segments (up to 1,000 feet at a time), with each segment typically taking 1-5 days to complete, depending on the depth of excavation. Doorhangers will be used to communicate with residents, and crews may also coordinate directly with homeowners, as necessary. 

Please be alert for any traffic controls or safety measures. For any urgent questions or issues, call (916) 995-0899 during work hours or (916) 875-6730 after hours. For more information, please visit sacsewer.com/highlands or call the project hotline at (916) 876-SASD (7273). 

Log in